Commonwealth Waterline Extension

Latest News:  Waterline is now complete! Currently, Lot S10 is slotted for Firestone Tire and S11 is slotted for a Popeye's Chicken. More to come! 

Project Overview

The City of Martinsville is undertaking the Commonwealth Waterline Extension, a vital infrastructure project aimed at supporting the city's growth and development. This initiative involves the installation of approximately 2,850 linear feet of new 8-inch waterline along Commonwealth Boulevard West, extending to Memorial Boulevard. The extension will provide water service to undeveloped properties on the south side of Commonwealth Boulevard, specifically around 12 lots.

Document

Timeline 

  • Approval: The project was approved by the Martinsville City Council on April 29, 2025.

  • Blasting: Complete

  • Development and Construction: Underway

Economic Impact

The extension is a key component in facilitating future development along Commonwealth Boulevard West. It is expected to pave the way for new commercial establishments, including national chains such as Chipotle, Popeyes, and a donut shop, all of which are planning locations in the area.

Summary

  • Scope: Installation of ~2,850 feet of 8-inch waterline along Commonwealth Boulevard West to Memorial Boulevard.

  • Purpose: Provide water service to approximately 12 undeveloped lots.

  • Approval Date: April 29, 2025.

  • Bidding Timeline:

    • Pre-Bid Meeting: May 22, 2025.

    • Bid Submission Deadline: June 10, 2025, at 1:30 PM.

  • Economic Impact: Supports the development of new commercial establishments, including Chipotle, Popeyes, and a donut shop.